−1,500 m · WATER COLUMN · FIELD NOTES

Blog

Seven Billion Spent, and the Bill Has Not Moved

The UK regulator's 2026 decommissioning update puts remaining UKCS decommissioning at £43.4 billion after a record £2.6 billion of spend in 2025. Held at one price basis, the same 2023-onwards programme has grown from £44.0 billion to £50.5 billion in four survey cycles. Wells are half the cost to 2032 and 40% of everything that remains; the largest single line is subsea well P&A; the binding constraint is six semi-submersibles.

  • decommissioning
  • wells
  • subsea
  • north-sea
  • regulation

The two numbers in the release

On 13 August 2026 the UK regulator published its annual decommissioning update. Its own headline carried two numbers: £2.6 billion spent on UK Continental Shelf decommissioning in 2025 — a basin record, against £2.4 bn in 2024 and £2.0 bn in 2023, in-year prices — and £43.4 billion of estimated remaining cost, down from £43.6 billion a year earlier, each survey in its own year's prices.

Read straight: £2.6 billion spent, outstanding bill down £0.2 billion. The report's own waterfall says why — the forecast is revised upward at every cycle, by more than the year's spend in three of the four: +£3.6 bn against nothing, +£5.4 bn against −£2.0 bn, +£2.6 bn against −£2.4 bn, and last cycle +£2.4 bn against −£2.6 bn. Inflation is one of the causes named.

Our arithmetic on the published figures

This section is subtraction and division performed by us on numbers printed in Figures 15 and 16. The inputs are the regulator's; the differences and percentages are ours.

Figure 16 restates the same scope — the whole programme from 2023 onwards — at one price basis (2025 prices), once per annual stewardship survey. The total reads:

£44.0 bn (UKSS 2021) → £45.7 bn → £48.8 bn → £49.7 bn → £50.5 bn (UKSS 2025).

Over the same cycles, spend of £2.1 + £2.5 + £2.6 = £7.2 billion was recorded — Figure 5 prints the same three, labelled — and the remaining forecast moved £44.0 bn → £43.4 bn. The report's "approximately £7 billion" is the in-year sum.

So: £7.2 billion was spent, the remaining bill fell by £0.6 billion, and the programme grew by £6.5 billion — 14.8% — in constant money. Figure 15 shows £36.3 bn → £41.8 bn in 2021 prices, and it has to: both panels rebase one HM Treasury deflator series (30 June 2026 release), so the base year cancels and the 15.2% there is the same number after rounding. Real growth against economy-wide inflation — though a GDP deflator does not remove rig and heavy-lift rates, which the report names among the causes. Scope and rates, not the index.

The report's own caveat: "Comparison against historic NSTA cost estimates is on a full portfolio best estimate basis and not like-for-like per project."

Two-panel chart on a dark navy background. Left panel: five horizontal stacked bars, one per annual UK Stewardship Survey from 2021 to 2025, all in constant 2025 prices for the decommissioning programme from 2023 onwards. Gold segments show spend already incurred — 2.1, 2.5 and 2.6 billion pounds accumulating across the surveys — and blue segments show the remaining forecast, which reads 44.0, 45.7, 46.7, 45.2 and 43.4 billion pounds. The report's own totals at the end of each bar rise from 44.0 to 50.5 billion pounds. Right panel: the four largest remaining cost categories from 2026 onwards, in billions of pounds — subsea well plug and abandonment 9.8, platform well plug and abandonment 7.3, topside and substructure removal 7.0, subsea infrastructure 5.0 — four of the eight categories in a narrower scope, decommissioning survey only, which is why they do not add up to the 43.4 billion on the left — and a box reading plus 6.5 billion pounds, plus 14.8 per cent, real growth over four survey cycles.

Where the money actually sits

Figure 10 breaks the 2023-onwards programme by WBS, in 2025 prices — totals, with what is still to spend in brackets:

  • Well P&A (subsea) — £11.1 bn (£9.8 bn remaining)
  • Well P&A (platform) — £9.2 bn (£7.3 bn)
  • Topside and substructure removal — £7.4 bn (£7.0 bn)
  • Subsea infrastructure — £5.4 bn (£5.0 bn)
  • the remaining four categories run from £4.3 bn down to £2.3 bn

Subsea well P&A is the largest single line item in the basin, and the least advanced: about £1.4 bn of its £11.1 bn has been spent in three years. Removals are almost entirely ahead: £7.0 bn of £7.4 bn on topsides and substructures, £5.0 bn of £5.4 bn subsea. Wells took over 50% of spend since 2023 and about 40% of what remains — the balance shifts toward steel, vessels and yards.

Mind the scope label: decom survey only. The eight categories sum to £40.0 bn remaining (our addition) against the £43.4 bn headline, which is total decommissioning and also carries onshore terminals, major pipelines and non-producing fields. Quoting one against the other is a way to be wrong by £3.4 bn.

The backlog is physical

About 3,000 wells remain to be fully plugged and abandoned. Figure 12a profiles them in seven five-year windows running to 2056–2060, and the cumulative Figure 12b ends at 1,989 platform, 1,030 subsea and 81 suspended E&A wells, 3,100 by our addition. The first window, 2026–2030, carries 902 platform, 404 subsea and 60 E&A wells.

Against that: in 2025 operators worked on 257 wells and 114 reached final AB3 status, up from 238 and 103 in 2024. Well abandonment cost £1,273 million in 2025, 49% of all decommissioning spend — the same share as 2024. The backlog awaiting final abandonment is "broadly unchanged" at about 500.

AB3 is a cutting job, not a barrier job

AB2 (derogated): in-well isolation complete, with derogation granted or pending to leave the well origin or the equipment above it, such as the conductor. AB3: in addition to the permanent barriers, "the well origin and all conductor equipment associated with the well origin have been removed."

That last step is not a pressure-containment operation. It is severance and lift at the seabed — and the regulator's stated aim is to "release valuable rig capacity for earlier-stage well abandonment work". The wellhead severance charter signed by the regulator and 17 operators in August 2026 is careful to stay neutral on the means, "including both vessels and rigs"; it "is not intended to have binding legal effect", and commits signatories to a workgroup, to data sharing and to early supply chain engagement.

The numbers for the prize: roughly 1,000 subsea wells left, £700,000 average per wellhead removal over five years on a sample of more than 100 wells, and a 30%, or about £200 million, reduction if vessels replace rigs — assuming every wellhead is removed and excluding inflation. Our check: 1,000 × £700,000 × 30% = £210 million, so £200 million is rounded down. It is also about 0.5% of the £43.4 bn (our division). The prize is not the money — it is the rig-weeks released for barrier work that only a rig can do.

The constraint is the fleet

Six semi-submersibles are marketed in the UKCS, down from a peak of eleven in 2023 — the NSTA's figure, sourced in its appendix to Westwood Global Energy, July 2026. The same units are wanted for production-adding interventions and for CCS drilling. The report also records a "marked increase in the cost of large (> 3kTe) removals of jackets and topsides", attributed to global demand for heavy lift vessels. Decommissioning is forecast to overtake capital expenditure from 2029, taking 24% of UK upstream spend in 2026–2031 against 13% in 2021–2025.

What we could not confirm

  • Appendix 1, Figure 17 forecasts removal quantities, tonnage and kilometres for 2026–2037 in seven panels, with no data labels — we quote nothing from it.
  • Figures 8a and 8b (operator concentration) carry no values in the PDF text layer. That one operator now accounts for 17% of the decade's expenditure and the top 10 for more than 80% comes from the body text; the report does not name them, and neither do we.
  • The Benchmarking Report 2026 is an interactive application we did not read; its ">1,280 wells" scope and the cited saving of over £250,000 per well on an eight-well campaign are the regulator's.

What to watch

  1. The rate gap. The 2026–2030 window holds 1,366 inactive wells (our sum of the three categories); 114 reached AB3 in 2025. Either the rate multiplies or the profile slides right.
  2. Whether severance actually moves to vessels. A non-binding charter is worth one campaign: the test is a multi-operator vessel campaign with a published unit cost.
  3. The next survey's "change in forecast" term. In three of four cycles it exceeded that year's spend; in the fourth it fell £0.2 bn short — and that £0.2 bn is the whole fall in the headline.
  4. CCS-driven P&A scope. Under net zero, reuse and repurposing, the risk register flags wells that may need decommissioning to a higher standard to enable CCS — "additional intermediate barriers and or intersect wells". A different well design, decided long before the rig arrives.

Sources

  1. NSTA (North Sea Transition Authority), UKCS Decommissioning Cost and Performance Update 2026, published 13 August 2026, 40 pages. Read in full from the PDF on 21 September 2026. Figures used: Figure 1 (annual spend, in-year prices), Figure 2 and Figure 3 (cost estimate by survey year and rolling forecast, in-year prices), Figure 5 (decade cost profile per year, 2025 prices), Figures 8a and 8b (operator concentration, unlabelled), Figure 9 and Figure 10 (Work Breakdown Structure cost share and cost per WBS category), Figures 12a and 12b (inactive well decommissioning profile by five-year window, 2026–2060), Figure 13 (UK upstream expenditure), Figures 14a and 14b (cost breakdown 2021–2025 and 2026–2031), Figure 15 (2021 prices) and Figure 16 (2025 prices), Table 1 (2025 actual cost and associated activity), Appendix 1 Figure 17, Appendix 2b (rig supply and demand, sourced by the NSTA to Westwood Global Energy, July 2026), Methodology and Glossary. Re-used under the NSTA User Agreement (June 2023): \"Contains information provided by the North Sea Transition Authority and/or other third parties.\" No figure from the report is reproduced; the chart is drawn from the published values.https://nstauthority.co.uk/media/w1fa3xvv/ukcs-decommissioning-cost-and-performance-update-2026.pdf
  2. NSTA, publication page for the UKCS Decommissioning Cost and Performance Update 2026, dated 13 August 2026. Accessed 21 September 2026.https://www.nstauthority.co.uk/news-publications/ukcs-decommissioning-cost-and-performance-update-2026/
  3. NSTA, Wellhead severance charter, August 2026, 4 pages. Read in full on 21 September 2026. Source of the charter's stated objectives, of the four principles signatories commit to, and of the statement that the charter 'is not intended to have binding legal effect'. Signed by the NSTA and 17 operators; the signatories are named in the document and are not reproduced here.https://www.nstauthority.co.uk/media/1aacyngy/wellhead-severance-charter.pdf
  4. NSTA, press release 'Leading North Sea operators back NSTA well decommissioning charter', 13 August 2026. Accessed 21 September 2026. Source of the wellhead severance figures quoted here: approximately 1,000 subsea wells remaining, an average cost per wellhead removal of £700,000 over the past five years on a sample of more than 100 wells, and an estimated reduction of about 30% or £200 million from using vessels instead of rigs, stated as assuming all wellheads are removed and not accounting for inflation.https://www.nstauthority.co.uk/news-publications/leading-north-sea-operators-back-nsta-well-decommissioning-charter/
  5. NSTA, UKCS Decommissioning Benchmarking Report 2026, published 13 August 2026. An interactive Power BI application covering more than 1,280 wells. Consulted as a landing page only — we did not read the underlying dataset, and no figure in this post comes from it.https://www.nstauthority.co.uk/news-publications/ukcs-decommissioning-benchmarking-report-2026/